Grid & curtailmentConsultationNational2026-11-25スマートジャパン (ITmedia)

Proposed measures to speed grid connection for data centres and grid batteries, including N-1 supply suspension and time-limited receiving restrictions

長期化するデータセンターや系統用蓄電池の系統接続、解消策に受電制限などを導入へ

At the 14th session of a Japanese government working group on power system connection, the agency set out concrete options for shortening grid-connection waits for data centers and grid-scale batteries, including allowing connection under an N-1 outage condition with time-limited power receipt restrictions. The source says data-centre power demand is expected to reach 762万kW by FY2035, but connection lead times are lengthening in some areas.

Why it matters: METI's next-generation grid working group presented concrete options for faster connection of large loads and grid-scale batteries, including conditional supply restrictions that could shorten long connection queues.

The details

  • Source: スマートジャパン (ITmedia), 25 Nov 2026, 07:00 JST; reports on the 14th session of the WG on power system connection (電力系統ワーキンググループ) under the agency.
  • Data-centre power demand is expected to rise to 762万kW by FY2035 (2035年度).
  • In some areas, grid-connection lead times are lengthening; causes cited include reserved grid capacity that is not fully used, plus construction workforce shortages and equipment procurement constraints.
  • Grid-connected storage applications, as of late September 2026 (per source): 22,235万kW for 接続検討 (connection study), 4,352万kW for 接続契約申込み (connection contract applications), and 169万kW connected (接続済み). The source notes these figures with a regional/monthly qualifier that is partly garbled.
  • Under current rules, grid-connected equipment must keep grid reliability even if one unit fails (N-1), so adding capacity may require additional transformers or other equipment.
  • Proposed measures include connecting data centers and storage on the premise of N-1 outage conditions for a limited time, and time-limited restrictions on power receipt (受電制限).
  • The source notes that facilities such as AI data centers could use storage or backup systems during outages.
  • The source states that grid reinforcement remains important; once grid works are carried out, connection without N-1 limits would apply.
日本語で読む

長期化するデータセンターや系統用蓄電池の系統接続、解消策に受電制限などを導入へ

  • 出典:スマートジャパン(ITmedia)、2026年11月25日7時00分公開。資源エネルギー庁の「電力系統ワーキンググループ」第14回会合の報道。
  • データセンターの電力需要は2035年度に762万kWへ増える見通し。
  • 一部地域では系統接続までの期間が長期化。背景として、確保された系統容量が十分に使われていないこと、工事の人材不足や機器調達の制約が挙げられています。
  • 系統用蓄電池の接続申込状況(2026年9月末時点、原文の注記による):接続検討 22,235万kW、接続契約申込み 4,352万kW、接続済み 169万kW。
  • 現行ルールでは、一台の設備が故障しても(N-1)系統の信頼性を保つ必要があり、増設には変圧器などの追加設備が必要になる場合がある。
  • 提案される方策:N-1停止を前提に一定期間の接続を認めること、一定時間帯の受電制限を設けること。
  • AIデータセンターなどは、停電時に蓄電池やバックアップ電源で対応する運用も考えられるとされています。
  • 系統増強の重要性は変わらず、系統工事を終えた後はN-1制限のない接続となる。