Grid & curtailmentOfficialHokkaido2026-11-26OCCTO 新着情報

OCCTO publishes verification results of renewable output curtailment due to grid congestion in Hokkaido (September 2026)

北海道エリアにおける流通設備混雑(系統制約)による再生可能エネルギー発電設備(自然変動電源)の出力抑制に関する検証結果の公表について(2026年9月分)

OCCTO has published its verification of Hokkaido Electric Power Network's September 2026 curtailment of renewable generators (variable renewable sources) caused by grid transmission congestion (系統制約). The body judged the curtailment instructions valid. Curtailment was carried out on each day of September 2026, mainly on the 66kV Iwamatsu line, with the 66kV Tomikawa line added on certain days.

Why it matters: Hokkaido Electric Power Network reports September 2026 curtailment of variable renewable generators caused by transmission congestion, relevant to developers and owners facing grid constraints in Hokkaido.

The details

  • Body: Organization for Cross-regional Coordination of Transmission Operators (OCCTO), under Article 180, paragraph 2 of its operating rules, verified the validity of curtailment instructions.
  • Operator: Hokkaido Electric Power Network Co., Ltd.
  • Area: Hokkaido; cause: transmission congestion (系統制約, grid constraint) on distribution facilities.
  • Period: all 30 days of September 2026 (1 to 30 September).
  • Facilities curtailed: 66kV Iwamatsu line (岩松線) every day; 66kV Tomikawa line (富川線) additionally on 6, 13, 20, 21, 22, 23 and 27 September.
  • Verification items: (1) specific content of curtailment under the output control rules; (2) necessity of curtailing renewable generation.
  • Result: the curtailment, carried out due to anticipated transmission congestion, was judged appropriate.
  • Attachments: Appendix 1 (specific content of control under output control rules); Appendix 2 (necessity of curtailing variable renewable sources); Appendix 3 (calendar).
  • Page updated 26 November 2026.
日本語で読む

北海道エリアにおける流通設備混雑(系統制約)による再生可能エネルギー発電設備(自然変動電源)の出力抑制に関する検証結果の公表について(2026年9月分)

  • 検証主体:広域機関(電力広域的運営推進機関)。業務規程第180条第2項に基づき、出力抑制に関する指令の妥当性を検証。
  • 実施者:北海道電力ネットワーク株式会社。
  • エリア:北海道。原因:流通設備の混雑(系統制約)。
  • 期間:2026年9月1日から9月30日までの全30日。
  • 抑制対象設備:66kV岩松線は毎日。66kV富川線は9月6日、13日、20日、21日、22日、23日、27日に追加。
  • 検証項目:(1) 出力制御ルールに基づく出力抑制の具体的内容、(2) 自然変動電源の出力抑制を行う必要性。
  • 検証結果:流通設備混雑が見込まれたために行われた今回の再エネ出力抑制は妥当と判断。
  • 添付資料:別紙1(出力制御ルールに基づく制御の具体的内容)、別紙2(自然変動電源の出力抑制を行う必要性)、別紙3(カレンダー)。
  • 更新日:2026年11月26日。