2024-12-20株式会社fantasista

2024年11月度系統用蓄電所事業用地取得及び電力会社への接続検討回答進捗状況に関するお知らせ(茨城県つくば市案件)

Notice on November 2024 progress of grid battery storage site acquisitions and grid connection study responses (Tsukuba, Ibaraki case)

株式会社fantasistaは、2024年12月20日時点の系統用蓄電所事業用地の取得状況と電力会社への接続検討回答の進捗を公表しました。取得済み14件(計28,362㎡)と今後の取得予定9件(計13,812㎡)の案件はいずれも8.14MWhとされています。つくば市案件(4,164㎡)は2024年9月30日に取得、10月22日に接続検討回答を得ています。子会社NCMAXWORLD株式会社の群馬太田案件は工事着工済みで、運転開始は2025年8月1日(予定)です。

  • Tsukuba case: land acquired (September 30, 2024), connection study response received October 22, 2024. Gunma Ota subsidiary project: under construction, operation planned August 1, 2025. Other sites: acquired or planned, with connection responses pending or planned.
  • 茨城県つくば市(本件)ほか、複数都道府県の案件
  • 8.1 MWh
  • 株式会社fantasista
  • NCMAXWORLD株式会社
  • 電力会社(社名記載なし)

詳細

  • 公表日:2024年12月20日(16時06分)。発行者は株式会社fantasista(東京都中央区銀座1-16-1 東貨ビル8階、東証スタンダード、代表者 田野 大地)。
  • 対象:記載の全案件は8.14MWhの蓄電池容量とされています。
  • 1.取得済み蓄電所事業用地と接続検討回答(14件、計28,362㎡、公簿地積)
  • 茨城県土浦市案件①:1,834㎡、売買契約2024年6月30日、取得2024年7月30日、接続検討回答10月22日。
  • 福井県越前市案件:851㎡、契約2024年6月30日、取得2024年7月31日、回答待ち。
  • 茨城県土浦市案件②:643㎡、契約2024年6月30日、取得2024年9月26日、回答10月28日。
  • 福井県大野市案件:1,303㎡、契約2024年6月30日、取得2024年9月30日、回答待ち。
  • 茨城県小美玉市案件:2,073㎡、契約2024年6月30日、取得2024年9月30日、回答10月22日。
  • 福井県坂井市案件①:673㎡、契約2024年6月30日、取得2024年9月17日、回答待ち。
  • 福井県坂井市案件②:992㎡、契約2024年6月30日、取得2024年9月30日、回答待ち。
  • 茨城県水戸市案件:1,568㎡、契約2024年6月30日、取得2024年9月30日、回答10月22日。
  • 茨城県土浦市案件③:9,226㎡、契約2024年6月30日、取得2024年10月8日、回答10月29日。
  • 茨城県つくば市案件:4,164㎡、契約2024年6月30日、取得2024年9月30日、回答10月22日。
  • 滋賀県東近江市案件:1,342㎡、契約2024年7月10日、取得2024年7月10日、回答待ち。
  • 兵庫県姫路市案件:1,140㎡、契約2024年8月9日、取得2024年8月9日、回答待ち。
  • 兵庫県相生市案件:984㎡、契約2024年8月9日、取得2024年8月9日、回答11月27日。
  • 福島県岩瀬郡案件:1,569㎡、契約2024年8月9日、取得2024年8月9日、回答12月11日。
  • 用語:接続検討とは、蓄電池設置時に電力会社(電力系統)との技術的な連系可否、必要な設備や対策、費用などを検討する手続き。
  • 2.今後の取得予定案件(9件、計13,812㎡、いずれも8.14MWh)
  • 奈良県大和高田案件:3,568㎡、売買契約・取得とも2025年1月末日予定、回答9月5日(記載どおり)。
  • 京都市右京区案件:1,859㎡、2025年1月末日予定、回答待ち。
  • 茨城県北茨城市案件:1,270㎡、2025年1月末日予定、回答12月17日。
  • 岡山県津山市案件:1,096㎡、2025年1月末日予定、回答待ち。
  • 石川県加賀市案件①・②・③:627㎡・538㎡・583㎡、2025年2月末日予定、回答待ち。
  • 三重県四日市市案件:1,472㎡、2025年2月末日予定、回答待ち。
  • 福井県勝山市案件:606㎡、2025年2月末日予定、回答待ち。
  • 福井県丹生郡案件:655㎡、2025年2月末日予定、回答待ち。
  • 滋賀県犬上郡案件:1,538㎡、2025年2月末日予定、回答待ち。
  • 用語:接続検討回答とは、電力会社から、蓄電所と電力系統の送配電線接続に関する技術的検討を踏まえた連携承諾、工事費負担金及び工期等についての回答。
  • 3.子会社案件(NCMAXWORLD株式会社):群馬県太田市案件、766㎡、売買契約2023年12月22日、取得2024年8月30日、蓄電池容量8.14MWh。2024年12月10日付のお知らせで本建設工事の着工を公表済み。運転開始日は2025年8月1日(予定)で、本日時点で変更なし。参考PDFリンクあり。
  • 4.先月からの変動:取得済み14件のうち、兵庫県相生市案件と福島県岩瀬郡案件の接続検討回答は、それまで回答待ちでしたが、2024年11月27日および12月11日に電力会社から回答を得た。その他の取得済み案件は引き続き回答待ち。新たに福井県勝山市案件、福井県丹生郡案件、滋賀県犬上郡案件の計3件を2025年2月末日までに追加取得する予定。その他の今後の取得予定も「2024年2月末日」までに取得予定と記載(原文のまま、2025年の誤記の可能性あり)。
Read in English

Notice on November 2024 progress of grid battery storage site acquisitions and grid connection study responses (Tsukuba, Ibaraki case)

  • Date of notice: December 20, 2024 (16:06), issued by 株式会社fantasista (Tokyo, Chuo-ku, Ginza 1-16-1; listed on TSE Standard; representative 田野 大地).
  • Scope: all projects listed are stated to be 8.14 MWh battery capacity.
  • Section 1, acquired storage sites and connection study responses (14 sites, total 28,362 m² per the land area, public register basis):
  • Ibaraki Tsuchiura case ①: 1,834 m²; sale contract June 30, 2024; acquired July 30, 2024; connection study response October 22.
  • Fukui Echizen case: 851 m²; contract June 30, 2024; acquired July 31, 2024; response pending.
  • Ibaraki Tsuchiura case ②: 643 m²; contract June 30, 2024; acquired September 26, 2024; response October 28.
  • Fukui Ono case: 1,303 m²; contract June 30, 2024; acquired September 30, 2024; response pending.
  • Ibaraki Omitama case: 2,073 m²; contract June 30, 2024; acquired September 30, 2024; response October 22.
  • Fukui Sakai case ①: 673 m²; contract June 30, 2024; acquired September 17, 2024; response pending.
  • Fukui Sakai case ②: 992 m²; contract June 30, 2024; acquired September 30, 2024; response pending.
  • Ibaraki Mito case: 1,568 m²; contract June 30, 2024; acquired September 30, 2024; response October 22.
  • Ibaraki Tsuchiura case ③: 9,226 m²; contract June 30, 2024; acquired October 8, 2024; response October 29.
  • Ibaraki Tsukuba case: 4,164 m²; contract June 30, 2024; acquired September 30, 2024; response October 22.
  • Shiga Higashiomi case: 1,342 m²; contract July 10, 2024; acquired July 10, 2024; response pending.
  • Hyogo Himeji case: 1,140 m²; contract August 9, 2024; acquired August 9, 2024; response pending.
  • Hyogo Aioi case: 984 m²; contract August 9, 2024; acquired August 9, 2024; response November 27.
  • Fukushima Iwase-gun case: 1,569 m²; contract August 9, 2024; acquired August 9, 2024; response December 11.
  • Definition given: 接続検討 is the procedure for assessing with the utility (power grid) the technical feasibility of interconnection, required equipment and measures, and costs when installing a battery.
  • Section 2, planned future acquisitions (9 sites, total 13,812 m²; all 8.14 MWh):
  • Nara Yamato-Takada case: 3,568 m²; contract and acquisition planned end of January 2025; response September 5 (as listed).
  • Kyoto Ukyo-ku case: 1,859 m²; contract and acquisition planned end of January 2025; response awaited.
  • Ibaraki Kitaibaraki case: 1,270 m²; contract and acquisition planned end of January 2025; response December 17.
  • Okayama Tsuyama case: 1,096 m²; contract and acquisition planned end of January 2025; response awaited.
  • Ishikawa Kaga cases ①, ②, ③: 627 m², 538 m², 583 m²; contract and acquisition planned end of February 2025; responses awaited.
  • Mie Yokkaichi case: 1,472 m²; contract and acquisition planned end of February 2025; response awaited.
  • Fukui Katsuyama case: 606 m²; contract and acquisition planned end of February 2025; response awaited.
  • Fukui Niu-gun case: 655 m²; contract and acquisition planned end of February 2025; response awaited.
  • Shiga Inukami-gun case: 1,538 m²; contract and acquisition planned end of February 2025; response awaited.
  • Definition given: 接続検討回答 is the utility's response on grid-connection approval after technical review, the construction cost burden and the construction period for connecting the storage site to the grid.
  • Section 3, subsidiary project (NCMAXWORLD株式会社): Gunma Ota case, 766 m²; sale contract December 22, 2023; acquired August 30, 2024; capacity 8.14 MWh. Construction start was announced in a December 10, 2024 notice; planned operation start August 1, 2025, unchanged as of the notice date. Reference PDF link provided.
  • Section 4, changes since last month: of the 14 acquired sites, the Hyogo Aioi and Fukushima Iwase-gun connection responses, previously pending, were received on November 27 and December 11, 2024. Other acquired sites remain awaiting responses. Three new planned projects (Fukui Katsuyama, Fukui Niu-gun, Shiga Inukami-gun; 3 in total) are to be acquired by end of February 2025. The company states other planned acquisitions are to be completed by end of February 2024 (sic, as written; likely a typo for 2025).