2026-10-23Yahoo!ニュース - Yahoo! JAPAN
[Grid-scale storage stations] Power balancing facilities surge amid solar growth and data center demand, sparking disputes (planned battery station on former factory site in Okitsu)
【 系統用蓄電 所】太陽光発電やデータセンター特需に伴い電力需給調整施設が急増しトラブルも ...(興津の工場跡地の蓄電所建設計画)
Grid-scale battery stations are rapidly increasing across Japan and Shizuoka, exemplified by Sala Energy's NAS-battery Sala Hamamatsu storage station opened in October 2025. A large storage project planned on a former factory site in Okitsu, Shimizu Ward, Shizuoka City, was cancelled on October 8 after resident opposition over noise and landscape, prompting the mayor to pursue siting rules including an ordinance. Kosai City already added grid batteries to its ordinance from April (Reiwa 8), requiring resident briefings.
- cancelled (Okitsu plan); Sala Hamamatsu operating
- 静岡県静岡市清水区興津
- サーラエナジー
Full account
- Sala Energy (gas supplier in western Shizuoka incl. Hamamatsu) opened the Sala Hamamatsu storage station at its supply center in October 2025.
- Uses NAS (sodium-based) batteries; multiple module batteries per container; capacity equals one day's use of 6,000 households. Connected directly to transmission lines.
- Motivation: surplus solar; Hamamatsu ranked No.1 nationally for solar installations count and volume for 10 straight years since FY2015.
- Noise measures: ducts curve exhaust sideways to reduce off-site noise from converters/cooling; site in industrial zone. Quotes from Ikeda Ikuhei, Sala Energy power business promotion dept.
- Agency for Natural Resources and Energy: grid-connected storage rose from 80,000 kW two years earlier to 1.28 million kW in June 2026 (16x). Connection applications: ~40 in FY2022 to ~3,900 in FY2025 (nearly 100x).
- Prof. Okubo Masashi (Waseda Univ.): lithium-ion prices fell to one-fifth in 10 years; data center demand from smartphones/AI also drives need; numbers likely to keep rising.
- Shimizu Ward, Shizuoka City: large storage station planned in June on former factory site in quiet residential Okitsu; August resident briefing drew 200+ people with noise and landscape concerns. Residents Sugiyama Kimihiro and Yamazaki Yosuke led a petition with 1,000+ supporters.
- October 8: developer release said it decided not to invest in some large projects; per sources, not due to opposition but residents' feelings were considered. Developer not named.
- City council member Yamanashi Wataru asked about an ordinance; Mayor Namba said legal siting regulation is insufficient, an ordinance is a strong option, warned of a 'second mega-solar problem', will hurry. National government regulates safety but not location.
- Kosai City (Ajioka Kazuki, environment section): amended ordinance covering solar to include grid batteries from April Reiwa 8 (this April), after inquiries rose about two years ago; requires resident briefings, agreements on request; non-compliance with recommendations leads to publication of developer name and reporting to national/prefectural governments.
日本語で読む
【 系統用蓄電 所】太陽光発電やデータセンター特需に伴い電力需給調整施設が急増しトラブルも ...(興津の工場跡地の蓄電所建設計画)
- サーラエナジー(浜松市など県西部でガス供給)が2025年10月、供給センターにサーラ浜松蓄電所を開設。
- NAS電池(ナトリウム使用)、コンテナ内に複数のモジュール電池。容量は一般家庭6000世帯分の1日使用量相当。送電線に直接接続。
- 背景:太陽光の余剰。浜松市は2015年度から10年連続で太陽光導入件数・導入量日本一。
- 騒音対策:ダクトで排気口を横向きにし敷地外へ音が出にくい構造。工業地域。電力事業推進部 池田郁平さん談。
- 資源エネルギー庁:系統接続蓄電所は2年前8万kWから2026年6月128万kWへ16倍。契約申込は2022年度約40件→2025年度約3900件(100倍近く)。
- 早稲田大学 大久保將史教授:リチウムイオン電池価格は10年で5分の1。データセンター需要も影響し、数は増える一方。
- 静岡市清水区興津の住宅街の工場跡地で6月に大規模蓄電所計画。8月の住民説明会に200人以上、騒音・景観の懸念。杉山公啓さん・山崎洋佑さんらの反対署名に1000人以上。
- 10月8日、事業者が「一部大型案件については投資を実施しないことを決定」と発表。関係者によると「反対運動が理由ではないが住民の気持ちを考慮した」。事業者名は記載なし。
- 市議会で山梨渉議員が質問、難波市長は法令上の規制が不十分、条例制定も有力案、「第二のメガソーラー問題」になりかねず作業を急ぐと答弁。国は安全規制のみで立地制限なし。
- 湖西市(環境課 味岡和季さん):2年ほど前から問い合わせ増加を受け、令和8年4月から条例対象に系統用蓄電池を追加。住民説明会開催、要望時の協定書締結を要求。勧告不服従時は事業者名・内容公表、国・県へ情報提供。