2026-10-01YUKU NEWS
Tokyo Century adds 1.5MW / approx. 6MWh battery to Iizuka solar plant, switching to FIP at start of operation
東京センチュリー、飯塚の太陽光に1.5MW・約6MWh蓄電池 運転開始と同時にFIP移行
On October 1, 2026, Tokyo Century began operating a 1,500kW / approx. 6,000kWh battery co-located at the Fukuoka Iizuka No.1 Mega Solar Power Plant in Iizuka, Fukuoka, and simultaneously switched the plant from FIT to FIP. The GS Yuasa battery will be operated via Tensor Energy's AI-based Tensor Cloud platform for wholesale and balancing markets. It is the group's second FIP co-located battery after the Kumamoto Arao Mega Solar plant.
- operating
- 福岡県飯塚市
- 1.5 MW
- 6 MWh
- 東京センチュリー
- 京セラTCLソーラー
- GSユアサ
- テス・エンジニアリング
- Tensor Energy
Full account
- Date: battery began operation on October 1, 2026; sales scheme switched from FIT to FIP at the same time.
- Site: Fukuoka Iizuka No.1 Mega Solar Power Plant (福岡・飯塚第一メガソーラー発電所), Iizuka City, Fukuoka Prefecture.
- Battery: output 1,500kW, capacity approx. 6,000kWh, made by GS Yuasa, installed within the existing plant.
- Existing solar: 1,990kWac, began operating December 2018.
- Tokyo Century: owner/announcer; Kyocera TCL Solar (group company) operates and manages the plant.
- Tess Engineering, which built the solar facility, carried out the battery installation.
- Operation: Tensor Energy's integrated platform "Tensor Cloud", combining AI forecasting of generation and power prices with automated charge/discharge control for the wholesale electricity market and balancing (需給調整) market.
- Not a new generation build; adds storage to an operating solar plant to shift the timing of supply.
- Aims: store and supply renewable power otherwise lost to output curtailment, and absorb solar output fluctuation.
- Group's second FIP co-located battery, following Kumamoto Arao Mega Solar Power Plant (operating since June 2024), which uses the same platform.
- Not disclosed: capex, expected revenue from the battery, curtailment reduction.
- Source: PR TIMES press release.
日本語で読む
東京センチュリー、飯塚の太陽光に1.5MW・約6MWh蓄電池 運転開始と同時にFIP移行
- 2026年10月1日に蓄電池の運転開始、同時に売電方式をFITからFIPへ移行。
- 場所:福岡県飯塚市「福岡・飯塚第一メガソーラー発電所」。
- 蓄電池:出力1,500kW、容量約6,000kWh、GSユアサ製、既存発電所内に設置。
- 既設太陽光:出力1,990kWac、2018年12月運転開始。
- 東京センチュリーが発表。グループの京セラTCLソーラーが発電所を運営・管理。
- 太陽光設備の施工を担ったテス・エンジニアリングが蓄電池の設置工事を担当。
- 運用:Tensor Energyの統合運用基盤「Tensor Cloud」。AIによる発電量・電力価格予測と、卸電力市場・需給調整市場に対応する充放電自動制御を組み合わせる。
- 発電設備の新設ではなく、稼働中の太陽光に蓄電機能を追加し供給時間帯を調整する取り組み。
- 狙い:出力制御で活用できなかった再エネ電力の蓄電・供給、太陽光の出力変動の吸収。
- グループのFIP併設蓄電池として、2024年6月運転開始の熊本・荒尾メガソーラー発電所に続く2件目。荒尾でも同じ運用基盤を導入。
- 設備投資額、売電収入の見通し、出力制御の削減量は非公表。
- 出典:PR TIMESプレスリリース。