fantasista begins construction of grid-scale battery storage station in Shiga Prefecture
fantasistaが滋賀県で系統用蓄電所の建設を開始
fantasista began construction on October 14, 2026 of "fantasista nagahama PSS", a 1,999kW / 7,521kWh grid-scale battery station in Nagahama, Shiga, its group's second such project. Completion is planned for March 2027 and operation for April 2027, with Kansai Electric subsidiary E-Flow as aggregator and PowerX batteries. The company is also pursuing an extra-high-voltage project, "fantasista tokyo PSS", in Inagi, Tokyo.
- under construction
- 滋賀県長浜市
- 2 MW
- 7.5 MWh
- 株式会社fantasista
- NC MAX WORLD株式会社
- 合同会社fantasista battery 3
- E-Flow合同会社
- 関西電力
- 株式会社パワーエックス
- 富士電機株式会社
- ニシム電子工業株式会社
- スズカ電工株式会社
Full account
- fantasista Co., Ltd. began construction on 2026-10-14 of "fantasista nagahama PSS (Nagahama storage station)" in Nagahama City, Shiga Prefecture.
- Group's 2nd grid-scale battery project; completion planned March 2027, operation start April 2027.
- Site approx. 1,789.59 m²; rated output 1,999kW; storage capacity 7,521kWh (planned).
- Project owner: fantasista battery 3 LLC, 100% subsidiary of NC MAX WORLD Co., Ltd. (consolidated subsidiary of fantasista).
- Draws on know-how from 1st project "fantasista gunma PSS (Gunma Ota storage station)", operating since August 2025.
- Aggregator: E-Flow LLC (100% subsidiary of Kansai Electric Power); batteries: PowerX; PCS: Fuji Electric; EMS: Nishimu Electronics Industries; design/construction: Suzuka Denko.
- Equipment has obtained IPA's "JC-STAR" cybersecurity certification.
- Aims for extra-high-voltage (above 7,000V) storage; promoting "fantasista tokyo PSS" in Inagi City, Tokyo, accelerating preparations toward construction in coordination with government and residents.
- Background: curtailment is a nationwide issue; from April 2026, 30-minute day-ahead trading began in the balancing market; from August 2026 caps on grid connection applications were introduced.
- Competitors: ORIX started a 48MW/113MWh station in Wakayama in 2024 and in September 2026 began construction on projects totaling 145MW in Oita and Yamagata; Tokyu Land and others entering.
- Source: fantasista press release (PR TIMES).
日本語で読む
fantasistaが滋賀県で系統用蓄電所の建設を開始
- 株式会社fantasistaは2026年10月14日、滋賀県長浜市で「fantasista nagahama PSS(長浜蓄電所)」の建設を開始。
- グループ系統用蓄電池事業の第2号案件。2027年3月完工、同年4月運用開始予定。
- 敷地約1,789.59平方メートル、定格出力1,999kW、蓄電容量7,521kWh(計画)。
- 事業主体:合同会社fantasista battery 3(連結子会社NC MAX WORLD株式会社の100%子会社)。
- 2025年8月運用開始の第1号案件「fantasista gunma PSS(群馬太田蓄電所)」のノウハウを投入。
- アグリゲーター:E-Flow合同会社(関西電力100%子会社)、蓄電池:株式会社パワーエックス、PCS:富士電機株式会社、EMS:ニシム電子工業株式会社、設計・建設:スズカ電工株式会社。
- IPAのサイバーセキュリティ評価制度「JC-STAR」認証取得。
- 特別高圧(7,000ボルト超)蓄電所を目指し、東京都稲城市で「fantasista tokyo PSS」を推進中。行政・近隣住民等と連携し着工準備を加速。
- 背景:出力制御が全国的課題。2026年4月から需給調整市場で30分単位の前日取引開始。2026年8月から系統接続申込に上限。
- 競合:オリックスが2024年に和歌山県で48MW/113MWhの蓄電所を稼働、2026年9月に大分県・山形県で合計145MW規模に着工。東急不動産など異業種参入も。
- 出典:fantasistaプレスリリース(PR TIMES)。