2026-04-03SMTBリース株式会社
Investment participation in Libra GK (grid-scale battery storage, including Mie Prefecture)
合同会社リブラへの出資参画について(三重県の系統用蓄電所)
Sumitomo Mitsui Trust Panasonic Finance has invested in Libra GK, a fund managed by Tokyu Land that develops, owns and operates multiple grid-scale battery storage sites. Libra is jointly funded by eight domestic companies and targets six extra-high-voltage storage projects totalling about 174MW and about 30 billion yen. The projects are slated to begin operation sequentially from FY2027 onward.
- planned (sequential operation from FY2027)
- 北海道、青森県、宮城県、福島県、三重県、福岡県
- 174 MW
- 三井住友トラスト・パナソニックファイナンス株式会社
- SMTBリース株式会社
- 東急不動産株式会社
- 合同会社リブラ
- 三井住友信託銀行株式会社
- 株式会社IBeeT
- 芙蓉総合リース株式会社
- 野村不動産株式会社
- 前田建設工業株式会社
- 日鉄興和不動産株式会社
- 伊藤忠商事株式会社
- 株式会社リエネ
- 株式会社リエネ・エナジー
Full account
- Press release dated 2026-04-03 (issued via PR TIMES by SMTB Lease Co., Ltd.).
- Sumitomo Mitsui Trust Panasonic Finance (HQ: Minato-ku, Tokyo; President: Keiichi Hamano) invested in Libra GK.
- Tokyu Land Corporation (HQ: Shibuya-ku, Tokyo; President: Hiroaki Hoshino) serves as fund manager of Libra, which develops, owns and operates multiple grid-scale battery storage sites.
- Libra is jointly funded by 8 domestic companies, including the company and Sumitomo Mitsui Trust Bank (HQ: Chiyoda-ku, Tokyo; President: Gakutomo Yoneyama).
- Target: 6 extra-high-voltage grid-scale storage projects; total project cost about 30 billion yen; output about 174MW.
- Sequential start of operation from FY2027 onward.
- Locations: Hokkaido, Aomori, Miyagi, Fukushima, Mie, Fukuoka prefectures.
- Representative: Libra General Incorporated Association, executive officer Hiroyuki Tanaka.
- Investors: Tokyu Land, IBeeT, Fuyo General Lease, Nomura Real Estate Development, Maeda Corporation, Nippon Steel Kowa Real Estate, Sumitomo Mitsui Trust Bank, Sumitomo Mitsui Trust Panasonic Finance.
- Project management: Tokyu Land, ITOCHU Corporation.
- Battery procurement: ITOCHU Corporation.
- Asset management: RENEW (Rienne) Co., Ltd. (株式会社リエネ).
- O&M (planned): Rienne Energy (株式会社リエネ・エナジー), ITOCHU Corporation.
- Rationale: storage provides balancing capacity amid growing renewables, discharging at peak demand or generation shortfall to stabilize the grid; the company aims to keep contributing to storage expansion using Tokyu Land's development capability and knowledge from working with the 8 investors.
日本語で読む
合同会社リブラへの出資参画について(三重県の系統用蓄電所)
- 2026年4月3日発表(SMTBリース株式会社、PR TIMES)。
- 三井住友トラスト・パナソニックファイナンス株式会社(本社:東京都港区、取締役社長:浜野敬一)が合同会社リブラに出資参画。
- 東急不動産株式会社(本社:東京都渋谷区、代表取締役社長:星野浩明)がファンド・マネージャー。リブラは複数拠点の系統用蓄電所の開発、保有、運営を行う。
- 同社および三井住友信託銀行株式会社(本社:東京都千代田区、取締役社長:米山学朋)を含む国内8企業による共同出資。
- 特別高圧の系統用蓄電所6物件、総事業費約300億円、出力約174MW。
- 2027年度以降の順次運転開始に向けて推進。
- 所在地:北海道、青森県、宮城県、福島県、三重県、福岡県。
- 代表者:一般社団法人リブラ 職務執行者 田中博之。
- 出資者:東急不動産、IBeeT、芙蓉総合リース、野村不動産、前田建設工業、日鉄興和不動産、三井住友信託銀行、三井住友トラスト・パナソニックファイナンス。
- プロジェクトマネジメント:東急不動産、伊藤忠商事。
- 蓄電池調達:伊藤忠商事。
- アセット・マネジメント:株式会社リエネ。
- O&M(予定):株式会社リエネ・エナジー、伊藤忠商事。
- 再エネ導入拡大に伴う需給変動・系統安定性の課題に対し、調整力電源として系統用蓄電所の重要性が高まっていると説明。