2026-10-14日本経済新聞

Marubeni Shin-Denryoku and Sun Village complete entry of grid-scale batteries into the balancing market

丸紅新電力とサンヴィレッジ、系統用蓄電池の需給調整市場への参入を完了

Marubeni Shin-Denryoku and Sun Village announced that all four grid-scale battery projects first announced in October 2025 completed entry into Japan's balancing market in September 2026. The projects, developed and owned by Sun Village in Tochigi and Saitama prefectures, are operated by Marubeni Shin-Denryoku as aggregator.

  • operating
  • 栃木県足利市、埼玉県本庄市、埼玉県大里郡寄居町
  • 丸紅新電力
  • サンヴィレッジ
  • 丸紅

Full account

  • Press release dated 2026年10月13日 (October 13, 2026).
  • Concerns four grid-scale battery projects announced in a press release dated October 17, 2025; all completed entry into the balancing market (需給調整市場) in September 2026.
  • Projects developed and owned by Sun Village: Ashikaga, Tochigi; Honjo, Saitama (two projects, per text); and Yorii, Osato District, Saitama — four in total.
  • Marubeni Shin-Denryoku acts as aggregator, handling bidding and operation in power markets.
  • Market entry required passing reviews on connection to general transmission/distribution operators' dispatch systems and response performance; all four passed and began actual supply-demand operation.
  • Marubeni Shin-Denryoku has 20+ years of retail electricity experience; since October 2024 it has operated the Ina storage station (伊那蓄電所) owned by Marubeni Corporation, with many balancing-market operations.
  • Its battery operation contracts total 179MW.
  • Will combine bids in wholesale, balancing and capacity markets to ensure stable operation and maximize revenue.
  • The companies promote a "full-package" grid battery product for third parties: Sun Village provides land/grid rights, EPC and O&M; Marubeni Shin-Denryoku provides commissioning support, coordination with transmission/distribution operators and aggregation.
  • No capacities given for the four projects.
日本語で読む

丸紅新電力とサンヴィレッジ、系統用蓄電池の需給調整市場への参入を完了

  • 発表日:2026年10月13日。
  • 2025年10月17日付プレスリリースで発表した系統用蓄電池4案件が、2026年9月にすべて需給調整市場への参入を完了。
  • 対象はサンヴィレッジが開発・保有する栃木県足利市、埼玉県本庄市の2案件、および埼玉県大里郡寄居町の計4案件。
  • 丸紅新電力がアグリゲーターとして電力市場への入札および運用を担当。
  • 参入には一般送配電事業者の指令システムとの接続や応動性能の審査合格が必要で、4案件すべて合格し実需給を開始。
  • 丸紅新電力は20年以上の小売電気事業の実績を持ち、2024年10月より丸紅株式会社保有の伊那蓄電所で系統用蓄電池を運用。
  • 蓄電池の運用業務の受注は179MW。
  • 卸電力市場、需給調整市場、容量市場への入札を組み合わせ、安定稼働と収益最大化を図る。
  • 第三者向けに「系統用蓄電池のフルパッケージ商品」を推進:サンヴィレッジが土地・系統権利、EPC、O&Mを、丸紅新電力が試運転対応、一般送配電事業者との調整、アグリゲーション業務を提供。
  • 4案件の容量は記載なし。

Attached to: 本庄市・サンヴィレッジ・8MWh系統用蓄電所(仮称) →