2026-03-31YUKU NEWS
[Grid-scale battery business] Japan Battery Storage Development Organization's 2MW/5MWh Sanbongi storage station in Kamisato, Saitama receives power; two projects grid-connected in succession in March
【系統用蓄電池事業】日本蓄電開発機構、埼玉県上里町で2MW・5MWhの七本木蓄電所が受電 3月中に2案件連続で系統接続
Japan Battery Storage Development Organization (JESDI) announced on March 31, 2026 that its 2MW/5MWh Sanbongi (七本木) battery storage station in Kamisato, Saitama has completed power reception about three and a half months after construction began. It is JESDI's third storage site in Japan and came just four days after its Kaminara station received power, with the facility slated for use in the primary balancing market.
- power received (grid-connected)
- 埼玉県児玉郡上里町
- 2 MW
- 5 MWh
- 日本蓄電開発機構株式会社
- イー・トップ株式会社
- HOBE ENERGY株式会社
- 株式会社RUTILEA
Full account
- Announcement: March 31, 2026, by 日本蓄電開発機構株式会社 (JESDI)
- Project: 七本木蓄電所 (Sanbongi storage station), 埼玉県児玉郡上里町
- Capacity: 2MW output, 5MWh storage
- Construction start: December 15, 2025; power received after about 3.5 months
- JESDI's third domestic storage site, after 滋賀県愛荘町 and 上奈良蓄電所 in 埼玉県熊谷市
- Roles: JESDI is project owner overseeing overall development; イー・トップ株式会社 is EPC contractor; HOBE ENERGY株式会社 supplied the battery system; 株式会社RUTILEA is aggregator and operational support provider (AI-based charge/discharge control, support for entry into the balancing market)
- Equipment: HOBE ENERGY LFP (lithium iron phosphate) 5ft compact storage system, smaller than typical 20ft containers, suited to sites with narrow access routes or constraints
- Planned use: primary balancing (一次調整力) for grid frequency maintenance
- Kaminara station received power on March 27, 2026; Sanbongi followed just 4 days later, indicating capacity to run multiple projects in parallel
- Article notes rising expectations for operators able to rapidly handle site acquisition, design, construction, grid connection and market entry
日本語で読む
【系統用蓄電池事業】日本蓄電開発機構、埼玉県上里町で2MW・5MWhの七本木蓄電所が受電 3月中に2案件連続で系統接続
- 発表:2026年3月31日、日本蓄電開発機構株式会社(JESDI)
- 案件:七本木蓄電所(埼玉県児玉郡上里町)
- 規模:出力2MW、蓄電容量5MWh
- 2025年12月15日着工、約3カ月半で受電
- JESDIにとって滋賀県愛荘町、埼玉県熊谷市の上奈良蓄電所に続く国内3カ所目
- 役割:日本蓄電開発機構が事業主体として開発全体を統括、イー・トップ株式会社がEPC、HOBE ENERGY株式会社が蓄電池システム供給、株式会社RUTILEAがアグリゲーター兼運用支援事業者(AI活用の充放電制御、需給調整市場への参入支援)
- 設備:HOBE ENERGY製LFP(リン酸鉄リチウムイオン)方式5ftコンパクト型蓄電システム。一般的な20ftコンテナ型より小型で、搬入経路が狭い場所や制約の多い用地でも設置しやすい
- 用途:電力系統の周波数維持に活用される一次調整力向け設備として運用予定
- 上奈良蓄電所は2026年3月27日に受電、その4日後に本案件が受電し、複数案件の並行推進体制を構築
- 用地確保から市場参入までを短期間で実現できる事業者への期待が高まっていると記事は指摘