2026-11-10日経BP
Grid battery begins receiving power in Makurazaki City; developed jointly by Nihon Chikudenchi and others
枕崎市に蓄電所が受電開始、日本蓄電池など共同開発
The NC Makurazaki Sakuradai-higashimachi grid battery in Kagoshima Prefecture began receiving power on November 4, the fourth site of a seven-site joint project by Nihon Chikudenchi and Remix Point. Its rated output is 1,988 kW and rated capacity 8,146 kWh, with CATL batteries and TMEIC PCS.
- operating (began receiving power November 4)
- 鹿児島県枕崎市
- 2 MW
- 8.1 MWh
- 日本蓄電池
- リミックスポイント
- CATL
- TMEIC
- カンドー
- クラフティア
- デジタルグリッド
Full account
- Project: Nihon Chikudenchi (Chiyoda, Tokyo) and Remix Point are jointly developing grid-scale storage at seven sites nationwide.
- Makurazaki site: NC Makurazaki Sakuradai-higashimachi grid battery, Kagoshima Prefecture, began receiving power on November 4 (article dated 2026/11/09); the fourth site to do so.
- Rated output 1988 kW; rated capacity 8146 kWh.
- Equipment: CATL batteries and TMEIC power conditioning systems (PCS).
- Plans: procedures under way to enter three power markets; entry into the adjustment (需給調整) market is planned for around March 2027.
- Sites already receiving power: Yatsushiro... (as written: 熊本県玉名市), 仙台市, 福岡県嘉麻市, 鹿児島県枕崎市.
- Remaining three sites expected to start receiving power: 和歌山県海南市 in November 2026; 岐阜県揖斐川町 in December 2026; 長野市 in March 2027.
- Kasuga (Fukuoka) NC Kuchiharu storage: began operating for the adjustment market on October 20; rated output 1975 kW, rated capacity 8146 kWh; CATL batteries and TMEIC PCS; aggregator is Digital Grid (デジタルグリッド).
- Remix Point also acquired development land for 恵那岩村3蓄電所(仮称)in 岐阜県恵那市, its second owned high-voltage grid storage project in the prefecture. Planned: construction start around April 2027, power receipt late July 2027, adjustment market entry around autumn 2027.
- Remix Point targets 48 high-voltage grid storage sites by the March 2029 fiscal year, of which 25 are to be self-owned. With Enai land, self-owned projects including development stage total 12, a 48% progress rate against the self-owned target.
- Expected monthly sales per operating site: about 15 million yen.
- Nihon Chikudenchi installed batteries on October 21 at two sites under development: NC Izumo-shi Kunitomi-cho storage (Shimane Prefecture, Izumo City), designed and built by Kando (Shinjuku, Tokyo); and NC Minami-Aizu-machi Tajima storage (Fukushima Prefecture, Minamiaizu town), built by Craftier (クラフティア).
- Related article linked in the source: a storage facility used as emergency power during disasters in Takayama City (not detailed).
日本語で読む
枕崎市に蓄電所が受電開始、日本蓄電池など共同開発
- 事業:日本蓄電池(東京都千代田区)とリミックスポイントが全国7カ所で系統用蓄電所を共同開発。
- 枕崎市:鹿児島県「NC枕崎市桜山東町蓄電所」が11月4日に受電を開始。同プロジェクトの4カ所目。
- 定格出力1988kW、定格容量8146kWh。
- 機器:CATL製蓄電池、TMEIC製パワーコンディショナー(PCS)。
- 計画:電力3市場への参入手続きを進める。需給調整市場への参入は2027年3月頃を予定。
- 受電済み:熊本県玉名市、仙台市、福岡県嘉麻市、鹿児島県枕崎市。
- 残り3カ所の受電開始見込み:和歌山県海南市(2026年11月)、岐阜県揖斐川町(同年12月)、長野市(2027年3月)。
- 嘉麻市「NC口春蓄電所」:10月20日から需給調整市場向けに運用開始。定格出力1975kW、定格容量8146kWh。CATL製蓄電池、TMEIC製PCS。アグリゲーターはデジタルグリッド。
- リミックスポイント:岐阜県恵那市で県内2カ所目の自社保有高圧系統用蓄電所「恵那岩村3蓄電所(仮称)」の開発用地を取得。2027年4月頃着工、同年7月下旬受電開始、同年秋頃に需給調整市場へ参入予定。
- 目標:2029年3月期までに高圧系統用蓄電所48カ所の開発、うち25カ所を自社保有。恵那市用地取得により開発段階を含む自社保有案件は計12カ所、目標に対する進捗率48%。
- 稼働済み施設1カ所あたりの月間見込売上高は約1500万円を想定。
- 日本蓄電池は10月21日、開発中の2カ所に蓄電池を設置。島根県出雲市「NC出雲市国富町蓄電所」はカンドー(東京都新宿区)が設計・施工、福島県南会津町「NC南会津町田島蓄電所」はクラフティアが施工。
- 関連記事:高山市で蓄電所が災害時の非常用電源として活用(詳細未記載)。