2026-10-04毎日新聞
[Miyawaka Storage Station continues post-completion operational preparations] Equipment inspection and maintenance carried out in September
[宮若蓄電所で竣工後の運用準備を継続]9月に設備点検・保守対応を実施、試験完了後の実務工程を推進
Sustainable Holdings says its grid-scale battery project "Miyawaka Storage Station" in Miyawaka, Fukuoka, completed aggregator testing in August 2026. In September 2026 the company continued post-completion work: equipment checks, maintenance, coordination with the manufacturer on parts replacement, and review of interconnection test information. No capacity figures are given.
- completed; post-completion operational preparation (aggregator testing completed)
- 福岡県宮若市
- サステナブルホールディングス株式会社
Full account
- Company: Sustainable Holdings Co., Ltd. (サステナブルホールディングス株式会社), developing the grid-scale battery "Miyawaka Storage Station" (宮若蓄電所) in Miyawaka City, Fukuoka Prefecture.
- Aggregator testing was completed in August 2026.
- In September 2026 the company:
- checked equipment condition
- carried out maintenance
- coordinated with the manufacturer on necessary parts replacement
- confirmed information related to interconnection (連接) testing
- The company says completing the equipment and running it in the market are separate stages.
- The system comprises batteries, PCS, EMS, high-voltage equipment and communications equipment, and exchanges data with external systems such as aggregators.
- After completion, both the individual equipment and the system as a whole must be checked.
- The company manages the whole project process: land development, grid connection, permits, equipment design, construction, and post-completion testing and operational preparation.
- It will continue working with related parties toward stable operation.
- The release shows an image of the company's grid-scale battery product "Raptor".
- No MW/MWh capacity, cost or commercial start date is given.
- Corporate profile:
- Businesses: water, glamping and renewable energy
- Representative Director: Kenta Mogi (茂木 健太)
- Headquarters: SAKURA Tower 6F, Shibuya Sakura Stage, 3-2 Sakuragaoka-cho, Shibuya-ku, Tokyo
- Distributed via PR TIMES on 2026/10/3.
日本語で読む
[宮若蓄電所で竣工後の運用準備を継続]9月に設備点検・保守対応を実施、試験完了後の実務工程を推進
- サステナブルホールディングス株式会社が、福岡県宮若市で系統用蓄電池「宮若蓄電所」を開発中。
- 2026年8月にアグリゲーターによる試験を完了。
- 2026年9月の実施内容:
- 設備状態の確認
- 保守対応
- 必要な部品交換に向けたメーカーとの調整
- 連接試験に関する情報確認
- 「設備完成」と「市場運用」は異なる工程であると説明。
- 蓄電池、PCS、EMS、高圧設備、通信設備が連携し、アグリゲーター等の外部システムと情報をやり取りして運用される。
- 竣工後は設備単体とシステム全体の双方を確認。
- 土地開発、系統連系、許認可、設備設計、施工から竣工後の試験・運用準備までを一連の工程として管理。
- 今後も関係事業者と連携し、安定運用に向けた工程を推進する。
- 系統用蓄電池製品「Raptor(ラプター)」の外観イメージを掲載。
- 容量(MW/MWh)、費用、運転開始日の記載なし。
- 会社概要:
- 事業内容: 水事業、グランピング事業、再生可能エネルギー事業
- 代表取締役: 茂木 健太
- 所在地: 東京都渋谷区桜丘町3番2号 渋谷サクラステージ SAKURAタワー6階
- PR TIMES配信(2026/10/3)。
Attached to: 宮若蓄電所 →