2026-11-10日経BP

Storage plant in Makurazaki City begins receiving power; jointly developed by Nihon Chikudenchi and others

枕崎市に蓄電所が受電開始、日本蓄電池など共同開発

Nihon Chikudenchi and Remix Point are jointly developing grid-scale battery storage plants at seven sites nationwide. The NC Makurazaki Sakuradai-higashi-cho storage plant in Kagoshima Prefecture began receiving power on November 4 as the project's fourth site, with a rated output of 1,988 kW and rated capacity of 8,146 kWh.

  • operating (grid power receipt started November 4; balancing market entry planned around March 2027)
  • 鹿児島県枕崎市
  • 2 MW
  • 8.1 MWh
  • 日本蓄電池
  • リミックスポイント
  • CATL
  • TMEIC
  • デジタルグリッド
  • カンドー
  • クラフティア

Full account

  • Date of article: 2026/11/09; author: 工藤宗介 (technical writer)
  • Nihon Chikudenchi (Chiyoda-ku, Tokyo) and Remix Point are jointly developing grid-scale storage plants (系統用蓄電所) at 7 sites nationwide.
  • Fourth site: NC Makurazaki Sakuradai-higashi-cho storage plant (NC枕崎市桜山東町蓄電所), Makurazaki City, Kagoshima Prefecture, began receiving power on November 4.
  • Rated output 1988 kW; rated capacity 8146 kWh.
  • Battery: CATL (China); power conditioner (PCS): TMEIC.
  • Plans to proceed with procedures to enter three electricity markets; entry to the balancing (需給調整) market is planned for around March 2027.
  • Sites that have now begun receiving power: Tamana (Kumamoto Prefecture), Sendai City, Kama City (Fukuoka Prefecture), and Makurazaki City (Kagoshima Prefecture).
  • Remaining three sites expected to begin receiving power: Kainan City (Wakayama Prefecture) in November 2026; Ibigawa Town (Gifu Prefecture) in December 2026; Nagano City in March 2027.
  • NC Kuchiharu storage plant (NC口春蓄電所) in Kama City began operating for the balancing market on October 20: rated output 1975 kW, rated capacity 8146 kWh; CATL batteries and TMEIC PCS; aggregator is Digital Grid (デジタルグリッド).
  • Remix Point acquired development land for 'Ena Iwamura 3 storage plant (provisional name)' in Ena City, Gifu Prefecture, its second self-owned high-voltage grid storage project in the prefecture. Planned: construction start around April 2027, power receipt late July 2027, balancing market entry around autumn 2027.
  • Remix Point targets 48 high-voltage grid storage plants developed by the fiscal year ending March 2029, of which 25 to be self-owned. With the Ena land, self-owned projects including those in development total 12, reaching 48% progress against the self-owned target.
  • Expected monthly sales of about 15 million yen per operating plant.
  • Nihon Chikudenchi installed batteries on October 21 at two plants under development: NC Izumo Kunitomi-cho storage plant (Izumo City, Shimane Prefecture), designed and built by Kando (Shinjuku-ku, Tokyo); NC Minamiaizu Tajima-cho storage plant (Minamiaizu Town, Fukushima Prefecture), built by Craftia (クラフティア).
  • Related article mentioned: storage plant used as emergency power source in disasters, Takayama City (not detailed).
日本語で読む

枕崎市に蓄電所が受電開始、日本蓄電池など共同開発

  • 記事日付:2026/11/09、執筆:工藤宗介(技術ライター)
  • 日本蓄電池(東京都千代田区)とリミックスポイントは、全国7カ所で系統用蓄電所の共同開発を進めている。
  • 4カ所目:鹿児島県枕崎市の「NC枕崎市桜山東町蓄電所」が11月4日に受電を開始。
  • 定格出力1988kW、定格容量8146kWh。
  • 蓄電池:CATL製、パワーコンディショナー(PCS):TMEIC(ティーマイク)製。
  • 電力3市場への参入に向けた手続きを進める計画。需給調整市場への参入は2027年3月頃を予定。
  • 受電済みは、熊本県玉名市、仙台市、福岡県嘉麻市、鹿児島県枕崎市の4カ所。
  • 残り3カ所の受電開始見込み:和歌山県海南市が2026年11月、岐阜県揖斐川町が同年12月、長野市が2027年3月。
  • 嘉麻市の「NC口春蓄電所」は10月20日から需給調整市場向けの運用を開始。定格出力1975kW、定格容量8146kWh。CATL製蓄電池とTMEIC製PCS。アグリゲーターはデジタルグリッド。
  • リミックスポイントは岐阜県恵那市で「恵那岩村3蓄電所(仮称)」の開発用地を取得(県内2カ所目の自社保有高圧系統用蓄電所)。2027年4月頃着工、同年7月下旬受電開始、同年秋頃に需給調整市場へ参入を予定。
  • 2029年3月期までに高圧系統用蓄電所48カ所の開発を目標、うち25カ所を自社保有する計画。恵那市の用地取得後、開発段階を含む自社保有案件は合計12カ所、目標に対する進捗率は48%。
  • 稼働済み施設1カ所あたりの月間見込売上高は約1500万円を想定。
  • 日本蓄電池は10月21日、開発中の2カ所に蓄電池を設置:島根県出雲市の「NC出雲市国富町蓄電所」(カンドー(東京都新宿区)が設計・施工)、福島県南会津町の「NC南会津町田島蓄電所」(クラフティアが施工)。
  • 関連記事として高山市の災害時非常用電源活用に言及(詳細なし)。