枕崎市 Battery Storage Plant Begins Receiving Power; Developed Jointly by Nihon Chikudenchi and Others

枕崎市に蓄電所が受電開始、日本蓄電池など共同開発

Nihon Chikudenchi and Remix Point have begun receiving power at NC枕崎市桜山東町蓄電所 in Makurazaki, Kagoshima, on November 4 (2026), the fourth of seven grid-scale storage sites in their joint programme. A sister site in Kagoshima's neighbour Kawara area (嘉麻市) started operating for the demand-adjustment market on October 20.

  • operating (grid power receipt started November 4, 2026)
  • 鹿児島県枕崎市
  • 2 MW
  • 8.1 MWh
  • 日本蓄電池
  • リミックスポイント
  • CATL
  • TMEIC
  • デジタルグリッド
  • カンドー
  • クラフティア

Full account

  • Publication date: 2026/11/09 16:19; author 工藤宗介 (technology writer).
  • Partners: 日本蓄電池 (Tokyo, Chiyoda-ku) and リミックスポイント jointly develop grid-scale storage at 7 sites nationwide.
  • Makurazaki site: NC枕崎市桜山東町蓄電所, Kagoshima Prefecture; began receiving power on November 4; 4th project site.
  • Rated output 1988 kW; rated capacity 8146 kWh.
  • Equipment: batteries from CATL (China); power conditioner (PCS) from TMEIC.
  • Plans to enter three electricity markets; entry into the demand-adjustment market (需給調整市場) planned around March 2027.
  • Sites now receiving power: 熊本県玉名市, 仙台市, 福岡県嘉麻市, 鹿児島県枕崎市 (4 sites).
  • Remaining three expected: 和歌山県海南市 (November 2026), 岐阜県揖斐川町 (December 2026), 長野市 (March 2027).
  • NC口春蓄電所 (嘉麻市): operating for demand-adjustment market since October 20; rated output 1975 kW; capacity 8146 kWh; CATL batteries and TMEIC PCS; aggregator is デジタルグリッド.
  • Remix Point acquired development land in 恵那市 (Gifu) for 高圧系統用蓄電所 「恵那岩村3蓄電所(仮称)」, its second self-owned project in the prefecture: construction around April 2027, power receipt late July 2027, demand-adjustment market entry around autumn 2027.
  • Remix Point targets 48 high-voltage grid storage sites by the fiscal year ending March 2029, of which 25 to be self-owned; with Enai land, self-owned projects including development stage total 12, a 48% progress rate toward the self-owned target.
  • Estimated monthly sales per operating site: about 15 million yen.
  • On October 21, Nihon Chikudenchi installed batteries at two sites under development: NC出雲市国富町蓄電所 (Shimane, Izumo; design and construction by カンドー, Tokyo Shinjuku-ku) and NC南会津町田島蓄電所 (Fukushima, Minamiaizu; construction by クラフティア).
  • Related article linked: 蓄電所が災害時の「非常用電源」に、高山市が活用.
日本語で読む

枕崎市に蓄電所が受電開始、日本蓄電池など共同開発

  • 発表日時:2026/11/09 16:19、執筆は工藤宗介(技術ライター)。
  • 共同開発者:日本蓄電池(東京都千代田区)とリミックスポイント。全国7カ所で系統用蓄電所を共同開発。
  • 枕崎市:「NC枕崎市桜山東町蓄電所」(鹿児島県)が11月4日に受電開始。同プロジェクトの4カ所目。
  • 定格出力1988kW、定格容量8146kWh。
  • 機器:CATL製蓄電池、TMEIC製パワーコンディショナー(PCS)。
  • 電力3市場への参入を計画。需給調整市場へは2027年3月頃を予定。
  • 受電済み:熊本県玉名市、仙台市、福岡県嘉麻市、鹿児島県枕崎市(4カ所)。
  • 残り3カ所の見込み:和歌山県海南市(2026年11月)、岐阜県揖斐川町(同年12月)、長野市(2027年3月)。
  • 「NC口春蓄電所」(嘉麻市)は10月20日から需給調整市場向けに運用開始。定格出力1975kW、定格容量8146kWh。CATL製蓄電池、TMEIC製PCS。アグリゲーターはデジタルグリッド。
  • リミックスポイントは岐阜県恵那市で用地を取得し、県内2カ所目の自社保有案件「恵那岩村3蓄電所(仮称)」(高圧系統用)を計画。2027年4月頃着工、同年7月下旬受電開始、同年秋頃に需給調整市場へ参入予定。
  • 2029年3月期に高圧系統用蓄電所48カ所の開発を目標とし、うち25カ所を自社保有予定。恵那市用地取得後、開発段階を含む自社保有案件は合計12カ所、進捗率48%。
  • 稼働済み施設1カ所あたりの月間見込売上高は約1500万円を想定。
  • 10月21日、日本蓄電池は開発中の2カ所で蓄電池を設置:「NC出雲市国富町蓄電所」(島根県出雲市、設計・施工はカンドー(東京都新宿区))、「NC南会津町田島蓄電所」(福島県南会津町、施工はクラフティア)。
  • 関連記事:蓄電所が災害時の「非常用電源」に、高山市が活用。