2026-04-03SMTBリース株式会社
Investment in Libra LLC (grid-scale battery storage stations, including Fukushima Prefecture)
合同会社リブラへの出資参画について(福島県の系統用蓄電所)
Sumitomo Mitsui Trust Panasonic Finance has invested in Libra LLC, a vehicle managed by Tokyu Land Corporation as fund manager that develops, owns and operates multiple extra-high-voltage grid-scale battery storage stations. Libra is jointly funded by eight domestic companies and targets six projects totaling about 174MW and about ¥30 billion in project costs, with sequential operation starting from FY2027 onward.
- planned (sequential operation from FY2027 onward)
- 北海道、青森県、宮城県、福島県、三重県、福岡県(6物件)
- 174 MW
- 三井住友トラスト・パナソニックファイナンス
- SMTBリース
- 東急不動産
- 合同会社リブラ
- 三井住友信託銀行
- IBeeT
- 芙蓉総合リース
- 野村不動産
- 前田建設工業
- 日鉄興和不動産
- 伊藤忠商事
- リエネ
- リエネ・エナジー
Full account
- Release dated 3 April 2026, 14:53, issued via PR TIMES by SMTB Lease Co., Ltd.
- Sumitomo Mitsui Trust Panasonic Finance Co., Ltd. (HQ: Minato-ku, Tokyo; President: Keiichi Hamano) invested in Libra LLC (合同会社リブラ).
- Tokyu Land Corporation (HQ: Shibuya-ku, Tokyo; President: Hiroaki Hoshino) acts as fund manager; Libra develops, owns and operates multiple grid-scale battery storage stations.
- Jointly funded by eight domestic companies, including Sumitomo Mitsui Trust Panasonic Finance and Sumitomo Mitsui Trust Bank (HQ: Chiyoda-ku, Tokyo; President: Gakutomo Yoneyama).
- Targets six extra-high-voltage grid-scale storage projects: total project cost approx. ¥30 billion (約300億円), output approx. 174MW; sequential start of operation from FY2027 onward.
- Locations: Hokkaido, Aomori, Miyagi, Fukushima, Mie and Fukuoka prefectures.
- Representative: Libra General Incorporated Association, executive officer Hiroyuki Tanaka.
- Investors: Tokyu Land, IBeeT, Fuyo General Lease, Nomura Real Estate Development (野村不動産), Maeda Corporation, Nippon Steel Kowa Real Estate, Sumitomo Mitsui Trust Bank, Sumitomo Mitsui Trust Panasonic Finance.
- Project management: Tokyu Land and ITOCHU Corporation.
- Battery procurement: ITOCHU Corporation.
- Asset management: Rienne (リエネ).
- O&M (planned): Rienne Energy (リエネ・エナジー) and ITOCHU Corporation.
- Rationale: growing renewables create challenges in handling supply-demand fluctuations and grid stability; storage discharges at peak demand or generation shortfall to stabilize the grid. The company will leverage Tokyu Land's development capability and knowledge from working with the eight investors to expand storage, and continue offering non-bank solutions toward decarbonization.
- No energy capacity (MWh) is given.
日本語で読む
合同会社リブラへの出資参画について(福島県の系統用蓄電所)
- 2026年4月3日14時53分、SMTBリース株式会社がPR TIMESで発表。
- 三井住友トラスト・パナソニックファイナンス株式会社(本社:東京都港区、取締役社長:浜野敬一)が合同会社リブラに出資参画。
- 東急不動産株式会社(本社:東京都渋谷区、代表取締役社長:星野浩明)がファンド・マネージャー。リブラは複数拠点の系統用蓄電所の開発・保有・運営を行う。
- 同社および三井住友信託銀行株式会社(本社:東京都千代田区、取締役社長:米山学朋)を含む国内8企業の共同出資。
- 特別高圧の系統用蓄電所6物件(総事業費約300億円、出力約174MW)を対象に、2027年度以降の順次運転開始に向け推進。
- 所在地:北海道、青森県、宮城県、福島県、三重県、福岡県。
- 代表者:一般社団法人リブラ 職務執行者 田中博之。
- 出資者:東急不動産、IBeeT、芙蓉総合リース、野村不動産、前田建設工業、日鉄興和不動産、三井住友信託銀行、三井住友トラスト・パナソニックファイナンス。
- プロジェクトマネジメント:東急不動産、伊藤忠商事。
- 蓄電池調達:伊藤忠商事。
- アセット・マネジメント:リエネ。
- O&M(予定):リエネ・エナジー、伊藤忠商事。
- 背景:再エネ導入拡大で需給変動対応・系統安定性確保が課題。蓄電所は需要が高い時間帯や発電不足時に放電し系統安定化に寄与。東急不動産の案件開発力と投資家8社との協働の知見を活かし普及拡大に貢献、ノンバンク機能を活かし脱炭素に向けたソリューションを提供していく。
- 容量(MWh)の記載なし。