2026-02-09YUKU NEWS
[Grid-scale battery business] PowerX to supply 48.6MWh of battery systems for six grid storage sites of Nomuraya Holdings
【系統用蓄電池事業】パワーエックス、野村屋ホールディングスの系統蓄電所6拠点向けに48.6MWhの蓄電システムを供給
PowerX announced on February 9, 2026 that it will supply 18 battery systems totaling 48.6MWh to six grid-scale storage sites developed by Nomuraya Holdings in Nagano, Gifu and Shizuoka prefectures. The sites will connect to the TEPCO or Chubu Electric areas and begin commercial operation in phases from spring 2026.
- planned (commercial operation from spring 2026)
- 長野県、岐阜県、静岡県
- 48.6 MWh
- パワーエックス
- 野村屋ホールディングス
Full account
- Announcement date: February 9, 2026, by PowerX, Inc.
- Customer/developer: Nomuraya Holdings Co., Ltd., developing six grid storage sites
- Supply: 18 units in total, total storage capacity 48.6MWh
- Products: grid-scale battery systems "Mega Power 2700A" and "Mega Power 2500"
- Locations: Nagano, Gifu and Shizuoka prefectures (three prefectures, six sites)
- Grid connection: TEPCO area or Chubu Electric area transmission/distribution networks
- Schedule: commercial operation to begin in phases from spring 2026
- Operation: charge during low-demand periods, discharge during high-demand periods, used as supply-demand balancing capacity
- Grid batteries are expected to address output fluctuations from expanding renewables and support flexible operation using electricity markets
- Systems are developed and manufactured by PowerX in Tamano City, Okayama Prefecture (domestically made)
- PowerX says it will continue to support grid stability and effective use of renewables, contributing to carbon neutrality
- Note: the page title refers to Site 2 (name not stated); no site-specific details are given
日本語で読む
【系統用蓄電池事業】パワーエックス、野村屋ホールディングスの系統蓄電所6拠点向けに48.6MWhの蓄電システムを供給
- 2026年2月9日、株式会社パワーエックスが発表
- 供給先:株式会社野村屋ホールディングスが開発する系統蓄電所6拠点
- 合計18台、総蓄電容量48.6MWh
- 採用製品:系統用蓄電システム「Mega Power 2700A」と「Mega Power 2500」の2機種
- 所在地:長野県、岐阜県、静岡県(3県6拠点)
- 接続:東京電力エリアまたは中部電力エリアの送配電網
- 2026年春から順次営業運転開始予定
- 需要が少ない時間帯に充電し、需要が高まる時間帯に放電、電力需給の調整力として活用
- 系統用蓄電池は再エネ導入拡大に伴う出力変動への対応や電力市場を活用した柔軟な需給運用を支える設備として期待
- 岡山県玉野市で開発・製造する国産システムを採用
- 同社は系統用蓄電池の普及を通じ電力系統の安定化と再エネ有効活用を支援し、カーボンニュートラル実現に貢献するとしている
- 注:タイトルは拠点2(名称記載なし)を指すが、拠点別の詳細は記載なし