2026-11-25ZDNET Japan
Orix starts operating 134 MW, Japan's largest-class battery storage plant in Maibara, Shiga Prefecture
【オリックス】滋賀県米原市で国内最大級134MWの蓄電所を運転開始
Orix Corporation will begin commercial operation of the Maibara Kohoku battery storage plant in Maibara, Shiga Prefecture, on December 1, which it says is one of Japan's largest-class storage plants. The 134 MW / 548 MWh lithium-ion facility is covered by the Long-term Decarbonization Power Source Auction and will begin operating under that scheme from April 2027.
- operating (commercial operation from December 1; long-term auction operation from April 2027)
- 滋賀県米原市
- 134 MW
- 548 MWh
- オリックス株式会社
- オリックス・リニューアブルエナジー・マネジメント株式会社
- 米原市
- 電力広域的運営推進機関(OCCTO)
Full account
- Operator: Orix Corporation (Minato-ku, Tokyo) is the project operator and manages the whole project.
- Name and location: Maibara Kohoku Battery Storage Plant (米原湖東蓄電所), Maibara City, Shiga Prefecture.
- Start date: commercial operation from December 1 (year not stated in the text).
- Site: Orix leases about 25,000 m² of city-owned land from Maibara City.
- Equipment: 140 lithium-ion battery containers.
- Rated output: 134 MW. Rated capacity: 548 MWh.
- Footnote: the rated capacity equals one day's electricity use of about 51,000 households, assuming one charge-discharge cycle per day and about 10.7 kWh/day per household, citing Ministry of the Environment data for FY2023.
- O&M (operation and maintenance): Orix Renewable Energy Management Corporation.
- Programme: the project is covered by the Long-term Decarbonization Power Source Auction, which provides, in principle for 20 years, fixed-cost-equivalent revenue from OCCTO. Operation under this scheme starts April 2027.
- Purpose: stable long-term revenue, and balancing supply and demand to support stable use of renewable energy.
- Background: renewables such as solar and wind have large output swings, so storage is spreading to balance supply and demand.
- Orix's storage business: entered in 2022; operates the Kinokawa storage plant (Wakayama, started 2024); developing the Yufu plant and the Yonezawa plant (see footnotes 4 and 5).
- Orix plans to expand storage nationwide through use of idle land in partnership with local governments and companies.
- Footnote 5 refers to a September 30, 2026 release on a jointly funded grid storage project with outside investors.
日本語で読む
【オリックス】滋賀県米原市で国内最大級134MWの蓄電所を運転開始
- 事業主体:オリックス株式会社(東京都港区)が事業全体を管理。
- 名称・所在地:「米原湖東蓄電所」、滋賀県米原市。
- 開始時期:12月1日から商業運転(年の記載なし)。
- 用地:米原市から市有地(約25,000㎡)を賃借。
- 設備:リチウムイオン蓄電池コンテナ140台。
- 定格出力134MW、定格容量548MWh。
- 注記:定格容量は1日1サイクルの充放電を前提に、一般家庭約5.1万世帯の1日の電力使用量に相当(1世帯当たり約10.7kWh/日、環境省データ(令和5年度)により算出)。
- 運営・維持管理(O&M):オリックス・リニューアブルエナジー・マネジメント株式会社。
- 制度:長期脱炭素電源オークション制度の対象。原則20年間、電力広域的運営推進機関(OCCTO)から固定費相当の収入を得られる仕組み。2027年4月から同制度を活用した運営を開始。
- 目的:長期的な安定収益の確保、蓄電池による需給調整を通じた再エネの安定利用。
- 背景:太陽光・風力は発電量の変動が大きく、需給調整を担う蓄電所の導入が進んでいる。
- オリックスの蓄電所事業:2022年に参入。「紀の川蓄電所」(和歌山県、2024年運転開始)の運営、「由布蓄電所」「米沢蓄電所」の開発を進める。
- 今後:自治体や企業と連携し遊休地を活用して全国で事業を拡大する方針。
- 注5:2026年9月30日付リリースで、外部投資家との共同出資による系統用蓄電所の初事業化を発表。
Attached to:紀の川蓄電所 →