2026-11-21RBB TODAY

Development of grid-scale battery project in Kumamoto City advances in earnest: farmland conversion permit obtained and equipment materials ordered

【熊本市で 系統用蓄電池 案件の開発を本格化】農地転用許可取得・資材発注を完了

Sustainable Holdings Co., Ltd. has obtained a farmland conversion permit and completed ordering battery storage equipment materials for a grid-scale battery project under development in Kumamoto City. The project targets site preparation starting in early December 2026, grid connection in February 2027, and handover after power receipt and pre-use inspection at the end of March 2027.

  • Permits obtained and equipment ordered; site preparation scheduled to begin December 2026 (pre-construction).
  • 熊本県熊本市
  • サステナブルホールディングス株式会社

Full account

  • Company: Sustainable Holdings Co., Ltd. (サステナブルホールディングス株式会社), which runs water, glamping and renewable energy businesses.
  • Project: grid-scale battery storage (系統用蓄電池) in Kumamoto City; exact location and project name not disclosed.
  • Product referenced: Raptor (ラプター) grid-scale battery product.
  • Status: farmland conversion permit (農地転用許可) obtained; storage equipment materials ordered in two separate orders, procurement procedures completed.
  • Kickoff meeting with related businesses held on 29 September 2026, covering permits, material procurement, ground treatment, equipment layout, communication lines and schedule; company says there is no major delay so far.
  • Site issues: some areas need ground-strength consideration; surface soil improvement (表層改良) planned on a limited area.
  • Equipment transport: cranes to carry in and install batteries, PCS and cubicles (キュービクル).
  • Schedule: site preparation (造成工事) starts early December 2026; communication line introduction and grid connection around February 2027; power receipt and pre-use inspection (使用前確認・自主点検) end of March 2027, followed by handover.
  • Progress meetings: monthly before site work starts, every two weeks after it starts.
  • Grid and communications: communication line introduction and grid connection assumed around February–March 2027; EMS connection, system integration, and post-power-receipt trial operation and data collection under coordination.
  • Market plan: after trial operation and data collection, enter the wholesale electricity market (JEPX), then after further tests, enter the demand-supply adjustment market (需給調整市場).
  • The company says it will manage progress of each project and aims for steady commercialisation of grid-scale batteries.
日本語で読む

【熊本市で 系統用蓄電池 案件の開発を本格化】農地転用許可取得・資材発注を完了

  • 会社:サステナブルホールディングス株式会社(水事業、グランピング事業、再生可能エネルギー事業)。
  • 案件:熊本市内の系統用蓄電池案件。所在地および案件名は非公表。
  • 製品:系統用蓄電池製品「Raptor(ラプター)」。
  • 進捗:農地転用許可を取得。蓄電設備の資材を2回に分けて発注し、発注手続きを完了。
  • 2026年9月29日に関係事業者とキックオフミーティングを実施。許認可、資材調達、地盤対策、設備配置、通信回線、工程を確認し、現時点で大きな遅延なく進行。
  • 地盤:敷地内の一部で地盤強度への配慮が必要。限定的な範囲で表層改良を実施する計画。
  • 搬入:クレーンで蓄電池、PCS、キュービクル等を搬入・設置する計画。
  • 工程:造成工事は2026年12月上旬開始。通信回線引き込み・系統連系は2027年2月。2027年3月末に受電および使用前確認(自主点検)を経て引き渡し。
  • 工程会議:造成工事開始前は月1回、開始後は2週間に1回を目安に実施。
  • 通信・系統連系:通信回線の引き込みは2027年2~3月頃を想定。EMS接続、システム連携、受電後の試運転・データ取得を関係事業者と調整。
  • 市場参入:試運転・データ取得後に卸電力市場(JEPX)へ参入し、その後の試験を経て需給調整市場への参入を目指す。
  • 会社は各案件の進捗を管理し、系統用蓄電池の着実な事業化を進めるとしている。