2026-10-16日経BP

Edison Power ends new battery storage plant development, citing worsening investment environment

エジソンパワー、蓄電所の新規開発を終了、投資環境の悪化で

Edison Power, based in Kisarazu, Chiba, announced on October 7 that it will end new development of grid-scale battery storage plants and will not invest in a planned large-scale project on the former Okitsu Shokuhin site in Shizuoka City. The company said an influx of new market entrants meant the project no longer met its investment criteria. It will instead focus on services such as factory-sited batteries, self-consumption solar-plus-storage, data center power and operations support.

  • cancelled
  • 静岡県静岡市(興津食品跡地)
  • 26 MW
  • 120 MWh
  • エジソンパワー

Full account

  • Article dated 2026/10/15 21:11; author: Sosuke Kudo, technical writer (Nikkei BP, Mega Solar Business plus).
  • Edison Power (Kisarazu, Chiba Prefecture) announced on October 7 that it is ending new development of grid-scale battery storage plants.
  • It decided not to invest in a large-scale grid storage plant it had planned on the former Okitsu Shokuhin (興津食品) site in Shizuoka City; this was planned as its 11th site.
  • The company currently operates 4 grid storage sites; including those under construction, its portfolio totals 10 sites, about 26 MW output and about 120 MWh capacity.
  • Through these projects it has built know-how in battery design, cleaning (清浄, as written) and construction, market operation, asset management, O&M, and EPC management.
  • Reason: many new entrants changed the market environment significantly. The company says it has emphasized investment discipline from the start, considering commissioning timing and market conditions, but excess entry means projects no longer meet its original investment criteria.
  • New basic policy: "Turning batteries from mere equipment into energy assets that create value," using its technical capability and operating experience to solve customer problems and create new revenue opportunities.
  • Priority businesses: factory-sited battery systems, self-consumption solar + battery systems, DC power/power supply systems, power for data centers, distributed energy, support for maximizing battery value, operations support and operation on behalf of clients, EPC and system integration.
  • According to Shizuoka Broadcasting (静岡放送), local residents in Shizuoka opposed the project over noise and fire risk, and a petition against it was conducted.
  • Edison Power states the cancellation was based solely on its investment criteria and not a response to the opposition.
日本語で読む

エジソンパワー、蓄電所の新規開発を終了、投資環境の悪化で

  • 記事日時:2026/10/15 21:11、工藤宗介=技術ライター(日経BP メガソーラービジネス plus)。
  • エジソンパワー(千葉県木更津市)は10月7日、系統用蓄電所の新規開発を終了すると発表。
  • 静岡市の興津食品跡地で建設を計画していた大規模系統用蓄電所案件(11サイト目)について投資を実施しないことを決定。
  • 現在4サイトの系統用蓄電所を運営し、建設中を含め合計10サイト、出力約26MW、容量約120MWh規模のポートフォリオを構築。
  • 蓄電池の設計・清浄・施工、市場運用、アセットマネジメント、O&M(運営・保守)、EPC(設計・調達・施工)マネジメントなどのノウハウを蓄積。
  • 多数の事業者の新規参入で市場環境が大きく変化。参入当初から運転開始時期や市場環境を踏まえ投資規律を重視してきたが、参入過多により当初の投資基準に見合わなくなったと判断。
  • 今後の基本方針は「蓄電池を単なる設備から価値を生み出すエネルギー資産へ」。技術力と実運用経験を活用し顧客の課題解決と新たな収益機会創出を支援。
  • 重点事業:工場併設型蓄電池システム、自家消費型太陽光・蓄電池システム、直流電源・給電システム、データセンター向け電源、分散型エネルギー、蓄電池価値の最大化支援、運用支援・運転代行、EPC・システムインテグレーション。
  • 静岡放送の報道によると、地域住民から騒音や火災のリスクなどを巡り反発があり、反対署名活動も行われていた。
  • エジソンパワーは、開発中止は投資基準に基づく判断であり、反対活動を受けての決定ではないと説明。