2026-11-25Re-urbanization -再都市化

140 Tesla Megapacks to be installed in Maibara, Shiga; Japan's largest-class storage plant to store about one day's power for roughly 50,000 households

テスラ製の大型蓄電池140台が滋賀・米原に 約5万世帯の1日分を蓄える国内最大級の蓄電所

Orix says its 134 MW / 548 MWh Yonehara Kotou storage plant in Maibara, Shiga, will start commercial operation on December 1 (the article gives 2026 for this date). The plant uses 140 Tesla Megapacks and connects directly to the Kansai power grid; its stored electricity equals about one day's use for roughly 50,000 households.

  • under construction; commercial operation planned for 2026-12-01
  • 滋賀県米原市番場
  • 134 MW
  • 548 MWh
  • オリックス
  • テスラ
  • 東芝プラントシステム
  • オリックス・リニューアブルエナジー・マネジメント
  • 関西電力
  • 三井住友信託銀行
  • 太陽生命

Full account

  • Project: 米原湖東蓄電所 (Yonehara Kotou storage plant), Maibara city, Shiga Prefecture, on about 2.5 ha of municipal land in 番場.
  • Equipment: 140 Tesla Megapack units; each Megapack combines battery, power conversion, temperature control and charge/discharge control in one enclosure, assembled at the factory.
  • Scale: rated output 134 MW, rated capacity 548 MWh; about 4.1 hours at rated output.
  • Households: about 50,000 households' one-day use; Orix's estimate assumes 10.7 kWh per household per day, giving about 51,000 households. Not equivalent to giving each home a full day of direct supply.
  • Comparison with 紀の川蓄電所 (Wakayama, co-developed by Orix and Kansai Electric, commercial operation 2024-12-01): 48 MW, 113 MWh, about 2.4 hours; Yonehara has about 2.8x the output and about 4.8x the energy.
  • Schedule: commercial operation announced as 2026-12-01 (planned); the city says completion on 2026-11-30 with operation the next day; construction started December 2024; Orix's announcement dated 2026-11-24.
  • Operation under 長期脱炭素電源オークション starts about four months after commercial operation, April 2027 (per article). Bid won in the FY2023 auction.
  • Revenue: long-term decarbonization power source auction pays fixed-cost-level revenue in principle for 20 years; for other-market revenue, about 90% is refunded.
  • Use case: stores surplus daytime solar, discharges after sunset. Article notes it does not generate power and cannot alone support all of Kansai.
  • Companies: Orix (establishes 米原湖東蓄電所合同会社, manages whole project); Tesla (supplies Megapack); 東芝プラントシステム (design, procurement, construction, commissioning, EPC); Orix Renewable Energy Management (OREM, O&M after operation).
  • Financing: project finance, repaid from storage revenue; 三井住友信託銀行 arranged syndicated loan; 太陽生命 participated.
  • Land: Maibara city leased the land in 2023 public call for unused land; 2024-04 to 23 years; annual rent 6.48 million yen; Orix selected.
  • Other Orix projects: Yufu city, Oita, and Yonezawa, Yamagata, built with external investor co-investment. A public-area multipurpose plaza with environmental signage and benches was also built.
  • Revenue markets described: wholesale market (arbitrage), adjustment market (fast charge/discharge), capacity market.
日本語で読む

テスラ製の大型蓄電池140台が滋賀・米原に 約5万世帯の1日分を蓄える国内最大級の蓄電所

  • 案件:米原湖東蓄電所(滋賀県米原市番場の市有地、約2.5ヘクタール)。
  • 設備:テスラ製Megapack140台。Megapackは蓄電池、電力変換装置、温度管理、充放電制御機器を一つの筐体にまとめ、工場で組み上げて出荷。
  • 規模:定格出力134MW、定格容量548MWh。定格出力での放電時間は約4.1時間。
  • 世帯換算:一般家庭約5万世帯の1日分。オリックスの試算は1世帯1日約10.7kWh、約5万1,000世帯分。各家庭に丸一日直接届けるという意味ではない。
  • 紀の川蓄電所(和歌山県、オリックスと関西電力が共同整備、2024年12月1日商業運転開始)との比較:48MW、113MWh、約2.4時間。米原は出力で約2.8倍、電力量で約4.8倍。
  • 日程:商業運転開始は2026年12月1日予定。市は2026年11月30日竣工、翌日運転開始と発表。2024年12月着工。オリックス発表は2026年11月24日。
  • 長期脱炭素電源オークションによる運営は商業運転開始から約4カ月後の2027年4月に開始(記事記載)。2023年度入札で落札。
  • 収入:原則20年間、固定費相当の収入を得る。他市場で得た対象収益は約9割を還付。
  • 仕組み:昼の太陽光余剰電力を取り込み、日没後に放電。蓄電所自体が発電するわけではなく、一カ所で関西全体の需給を支えるものでもない。
  • 企業:オリックス(米原湖東蓄電所合同会社を設立し事業全体を管理)、テスラ(Megapack供給)、東芝プラントシステム(設計・調達・建設・試運転を一括)、オリックス・リニューアブルエナジー・マネジメント(OREM、運営後の点検・修理などO&M)。
  • 資金調達:蓄電所の事業収入を返済原資とするプロジェクトファイナンス。三井住友信託銀行が協調融資を取りまとめ、太陽生命も参加。
  • 土地:米原市が2023年に未利用市有地の活用公募を実施。オリックスを選定し、2024年4月から23年間貸付。年額648万円。
  • その他:由布市(大分県)と米沢市(山形県)でも外部投資家との共同出資で建設を開始。敷地内に環境学習の看板やベンチを備えた多目的広場を整備。
  • 収益市場:卸電力市場(価格差)、需給調整市場(充放電の増減能力)、容量市場(長期脱炭素電源オークション)。