2026-10-04ストレートプレス
Miyawaka Battery Storage Station continues post-completion operational preparations: equipment inspection and maintenance carried out in September
【宮若蓄電所で竣工後の運用準備を継続】9月に設備点検・保守対応を実施、試験完了後の実務工程を推進
Sustainable Holdings says its grid-scale battery project, Miyawaka Battery Storage Station in Miyawaka, Fukuoka Prefecture, completed aggregator testing in August 2026. In September 2026 it continued post-completion work, including equipment checks, maintenance, coordination with the manufacturer on parts replacement and review of interconnection test information. The company says it will keep working with related parties toward stable operation.
- completed; aggregator testing done, pre-operation preparation and maintenance ongoing
- 福岡県宮若市
- サステナブルホールディングス株式会社
Full account
- Press release dated 2026-10-03 by Sustainable Holdings Co., Ltd. (サステナブルホールディングス株式会社).
- Project: grid-scale battery storage "Miyawaka Battery Storage Station" (宮若蓄電所), being developed in Miyawaka City, Fukuoka Prefecture.
- Product pictured: the company's grid-scale battery product "Raptor" (exterior image).
- August 2026: testing by an aggregator was completed.
- September 2026: in cooperation with the manufacturer, the company carried out equipment status checks and maintenance, coordinated on necessary parts replacement and reviewed information on interconnection (連接) testing.
- The company says the system involves multiple linked components: battery, PCS, EMS, high-voltage equipment and communication equipment. For market operation, communication and control with external parties such as aggregators also matter.
- The company stresses that "facility completion" and "market operation" are separate stages. A table of check and preparation steps was included as an image (contents not given in the text).
- The company manages the whole project process: land development, grid connection, permits, design, construction, and post-completion testing and operational preparation.
- FAQ: after testing, checks continue on equipment status, communication/control and maintenance. Manufacturer cooperation is needed for technical responses based on equipment specifications. Operational preparation will continue.
- No capacity (MW/MWh), commercial operation date, aggregator name or manufacturer name is given.
- Company profile: water, glamping and renewable energy businesses. Representative Director: Kenta Mogi (茂木 健太). Address: Shibuya Sakura Stage SAKURA Tower 6F, 3-2 Sakuragaokacho, Shibuya-ku, Tokyo.
日本語で読む
【宮若蓄電所で竣工後の運用準備を継続】9月に設備点検・保守対応を実施、試験完了後の実務工程を推進
- 2026-10-03付、サステナブルホールディングス株式会社のプレスリリース。
- 対象:福岡県宮若市で開発を進める系統用蓄電池「宮若蓄電所」。
- 掲載画像:系統用蓄電池製品 Raptor(ラプター)の外観イメージ。
- 2026年8月:アグリゲーターによる試験を完了。
- 2026年9月:メーカーとの連携のもと、以下を実施。
- 設備確認・保守対応
- 必要な部品交換に向けた調整
- 連接試験に関する情報確認
- 蓄電池、PCS、EMS、高圧設備、通信設備など複数設備の連携が必要で、市場運用ではアグリゲーター等外部事業者との通信・制御環境も重要としている。
- 「設備完成」と「市場運用」は異なる工程と強調。確認・準備工程の表は画像で掲載(本文に内容記載なし)。
- 同社は土地開発、系統連系、許認可、設備設計、施工から、竣工後の試験・運用準備までを一連の工程として管理。
- FAQ:
- 試験完了後も、設備状態、通信・制御、保守対応の確認を継続する。
- メーカー連携は、機器仕様に基づく技術的対応のため。
- 今後も運用準備を継続する。
- 容量(MW/MWh)、運転開始日、アグリゲーター名、メーカー名の記載なし。