2026-03-31日本蓄電開発機構株式会社
5MWh grid-scale battery 'Shichihongi Storage Station' energized in Kamisato, Saitama, following Kaminara Storage Station in consecutive March energizations, accelerating storage infrastructure build-out
埼玉県上里町で5MWh規模の系統用蓄電池「七本木蓄電所」を受電、上奈良蓄電所に続き3月での連続受電により、蓄電インフラ整備を加速
Japan Energy Storage Development Institute (JESDI) completed grid energization of the 2MW/5MWh Shichihongi Storage Station in Kamisato, Saitama, on March 31, 2026, about three and a half months after construction began. The site uses HOBE ENERGY's 5ft compact LFP systems and will provide primary control reserve. It follows the Kaminara Storage Station energized on March 27, 2026, and is JESDI's third site after Aisho, Shiga, and Kumagaya, Saitama.
- energized (受電完了)
- 埼玉県児玉郡上里町
- 2 MW
- 5 MWh
- 日本蓄電開発機構株式会社
- HOBE ENERGY株式会社
- 株式会社RUTILEA
- イー・トップ株式会社
Full account
- Developer/owner: 日本蓄電開発機構株式会社 (JESDI; HQ Tokyo; CEO 星野 晶; founded Oct 2024; capital ¥10 million; 東京都港区北青山2-12-4-303).
- Site: 七本木蓄電所, 埼玉県児玉郡上里町; JESDI's third domestic site after 滋賀県愛荘町 and 埼玉県熊谷市.
- Capacity: 2MW output / 5MWh.
- Role: primary control reserve (一次調整力) on the balancing market (需給調整市場) for frequency maintenance.
- Construction start: Dec 15, 2025; energized: Mar 31, 2026 (about 3.5 months).
- Equipment: HOBE ENERGY 5ft compact battery systems (LFP), EMS, and a substation container integrating PCS and step-up transformer. The 5ft units, versus industry-standard 20ft containers, allow installation at sites with narrow access or sharp curves.
- EPC/construction partner: イー・トップ株式会社; operations support/aggregator: 株式会社RUTILEA (using its power-trading optimization AI); battery supplier: HOBE ENERGY株式会社.
- Follows 上奈良蓄電所, energized Mar 27, 2026; JESDI cites its Shiga energization and market entry (2025) as the model. RUTILEA says the Aisho, Shiga site entered primary control reserve about 2 months after energization.
- Outlook: accelerate grid battery installations nationwide, with parallel handling of multiple projects from site selection through design, construction, grid connection and market-entry preparation.
- Quotes: 星野 晶 (JESDI) thanked partners and aims to build a nationwide track record combining speed and reliability. 沖野強一 (HOBE ENERGY) stressed a stable supply capability across multiple projects. 安富 貴浩 (RUTILEA) cited early market entry and AI-driven market operation. 飯塚 昌吾 (イー・トップ) said safety-first EPC management achieved completion on schedule.
日本語で読む
埼玉県上里町で5MWh規模の系統用蓄電池「七本木蓄電所」を受電、上奈良蓄電所に続き3月での連続受電により、蓄電インフラ整備を加速
- 事業者:日本蓄電開発機構株式会社(JESDI、本社東京都、代表取締役 星野 晶、2024年10月設立、資本金1,000万円、東京都港区北青山2-12-4-303)
- 蓄電所:七本木蓄電所(埼玉県児玉郡上里町)。滋賀県愛荘町、埼玉県熊谷市に続く国内第3の拠点
- 設備容量:5MWh(出力2MW)
- 役割:周波数維持のための一次調整力(需給調整市場)
- 着工日:2025年12月15日、受電日:2026年3月31日(約3か月半)
- 主要構成:HOBE ENERGY社製5ftコンパクト型蓄電システム(LFP)、EMS、PCSと昇圧変圧器一体型受変電コンテナ。業界標準の20ftコンテナに対し、狭小な搬入経路や急カーブの立地でも設置可能
- 建設パートナー(EPC):イー・トップ株式会社、運用支援(アグリゲーター):株式会社RUTILEA(電力取引最適化AIを活用)、蓄電池供給:HOBE ENERGY株式会社
- 2026年3月27日受電の上奈良蓄電所に続く案件。滋賀県での受電・市場参入実績(2025年)をモデルとして継承。愛荘町蓄電所は受電から約2か月で一次調整力に参入(RUTILEAコメント)
- 今後:全国で系統用蓄電池の設置を加速。用地選定から設計・施工・連系・市場参入準備までを複数案件で並行推進
- コメント:星野 晶氏(JESDI)は関係各社への謝意と、スピードと信頼性を備えた事業者として全国で実績を積む方針を表明。沖野強一氏(HOBE ENERGY)は複数案件に対応できる安定供給体制を強調。安富 貴浩氏(RUTILEA)は需給調整市場への早期参入とAIによる市場運用の高度化に言及。飯塚 昌吾氏(イー・トップ)は安全最優先で工程・品質を一元管理し、計画どおり完工したと述べた