OperatingChugoku · Bizen-shi, Okayama

Bizen City Honami High-voltage No. 2 Battery Storage Plant備前市穂浪高圧第2蓄電所

Power1.999MW
Energy8.14MWh
Duration4.1h
COD2026-06-01
Announced2022-04-01

GreenBee Energy, Inc. acquired the facility and began receiving power on 27 February 2026. Grid-connection testing was underway according to the 14 May disclosure. Wholesale electricity trading began on 1 June and balancing market trading (primary reserve) on 15 July. The transition to full-scale operation was announced on 17 September, and the 12 November quarterly results also confirmed the start of trading in both markets.

Participants

Developer
West Holdings Corporation
TNSP
Hokkaido Electric Power Network
Suppliers, aggregator, market details and sources are available to members.Sign in